|
Replacing
the Cruise Stage Sections
October 25, 2007
Photographs
© John Thomas
2007 |
 |
 |
 |
 |
 |
 |
On October 25 one of the two
sections of stage removed shortly after the visit of the QUEEN
ELIZABETH 2 were replaced by Smit tugs. The other removed section,
which contains the new pilot base was replaced on October 26. The
actual cruise stage, can following attention at Cammell Laird can
now be presumed to be complete. John Thomas also photographed the
old wooden hut which sits on top of the Prince's Jetty - one of the
first concrete structures of its kind wondering just how long the
new structure will last! |
|
Detailed Study of the Installation of the Prince's Landing Stage
Vehicle Bridge
September 18, 2007
Photographs
© Philip Dorricott
2007 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
A detailed study of the
installation of the new Prince's Landing Stage vehicle bridge on
September 18, 2007 |
|
Installing the New Prince's Stage Vehicle Bridge
September 18, 2007
Photographs
© 0242 Images |
 |
 |
 |
 |
 |
|
These photos were taken about 17.30
on Tuesday September 18 before the new stage vehicle bridge
was dropped the final few feet into position. The landward end had
been suspended from a steel beam supported on two multi wheel
trailers which had obviously moved forward as the bridge was pulled
into position. The outer end was being supported by the temporary
caisson which was holding it a couple of feet above the stage. The
outer corners were to land on steel plates with the central support
slotting into a groove cut on the stage. |
|
Prince's Stage - Preparing the Vehicle Bridge for Lifting
September 15, 2007
Photographs
© John H. Luxton |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
|
By Saturday September 15, 2007 preparations were
at an advanced stage to install the now completed road bridge which
will provide enhanced access to both the Isle of Man Steam Packet
Company and Cruise Terminal facilities. A large crane was in
position and lifting beams had been fitted to the bridge. It appears
that the river end of the bridge will be lifted onto the floating
caisson and and then moved out towards the stage. |
|
The
Cruise Terminal - Nearly Complete
September 15, 2007
Photographs
© John H. Luxton |
 |
 |
 |
 |
 |
 |
 |
Photographs of the Liverpool
Cruise Terminal on Saturday September 15, 2007 six days after the
visit of the first passenger ship
SEVEN SEAS VOYAGER. The stage is now virtually complete - though
some finishing off work appears to be required and the new vehicle
access bridge lifted into position by the large heavy lift crane
visble top right. |
|
Cruise
Terminal - Foot Bridge Installation
August 25, 2007
Photographs
© Chris Brindle |
_small.jpg) |
_small.jpg) |
_small.jpg) |
_small.JPG) |
_small.jpg) |
|
With all four sections of the cruise terminal
stage in place the foot bridge linking the stage to Prince's Parade
was craned into position on Saturday August 25. Only the new vehicle
bridge, currently under construction in St. Nicholas Place remains
to be moved into postition. |
|
Installing
The Second Section of The Cruise Terminal
August 21, 2007
Photographs
© Ian Collard |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
|
The second section of the Cruise Terminal departed
from Cammell Laird on Sunday August 19, 2007 top left. However, due
to adverse weather conditions it was taken into the Liverpool Dock
system until Tuesday August 21 when it was placed in position. The
third section which had not had to visit Cammell Laird was placed in
position on Wednesday August 22. Meanwhile construction of the new
vehicle bridge continues in St. Nicholas Place. However, it does
appear that at least some parts of the stage will have to be
returned to Laird's for dry docking after the September cruise
calls. |
|
Installing
the First Section of the Cruise Terminal
August 17, 2007
Photographs © John H. Luxton |
 |
 |
 |
 |
 |
|
The first section of stage
emerged from Cammell Laird #5 dry dock at 13:53 behind SMIT
GLADSTONE - it was then manoeuvred up river until the tide began to
ebb. The tugs SMIT TRAFALGAR, SMIT WATERLOO and SMIT GLADSTONE
brought the stage downstream to off Twelve Quays at around 16:20.
However, with inbound traffic due for Twelve Quays and SUPERSEACAT
TWO due at Prince's Stage the stage section was moved back up stream
. |
 |
 |
 |
 |
 |
|
It had been intended to install the stage after
the 19:00 departure of SUPERSEACAT TWO, however, due to late running
on her inbound sailing from Douglas she did not get away from
Liverpool until just after 20:00. However, before her departure the
tugs had brought the stage slowly back across the river. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
Once positioned the three tugs
easily pushed the stage into position. The operation of the pile
fixings are clearly shown with the stage being clamped on to the
dolphins by 20:39. There is an intended 5m gap between the stage
sections the bridging section can be seen on the deck of the stage
above. |
|
The ease with which the stage sections can be
fitted to the dolphins is noteworthy. This arrangement certainly
lends itself to the rapid removal of sections for maintenance should
that be necessary, unlike the traditional Mersey method of using
shore booms. |
|
Prince's
Landing Stage Continuing Work at Liverpool
August 11, 2007
Photographs © John H. Luxton |
|
 |
 |
 |
 |
Construction work on the
vehicle access bridge which will link the marshalling area to the
landing stage continues whilst the new foot passenger access bridge
has been delivered and rests on the pavement at what will be the
north end of the extended stage. |
 |
 |
 |
 |
 |
|
Vehicle turning bay in St. Nicholas Place |
Hopper Barge BLACK DEEP owned by
Niarchos Shipping and operated by GPS Marine Contractors has been
working in conjunction with a small suction dredger which is
removing silt from behind the landing stage. A similar operation was
carried out a few years ago. |
|
The Cruise
Terminal Stage In Dry Dock at Cammell Laird
August 11, 2007
Photographs © John H. Luxton |
 |
 |
 |
 |
 |
|
Two of the stage sections in Cammell Laird #5 dry
dock on Saturday August 11, 2007 one week after they arrived. |
|
Oh Dear
What Can The Matter Be?
The Cruise Terminal Stage Needs Dry Docking
Already!
August 04, 2007
Photographs © John H. Luxton & Alan Lee |
|
Rumours have been doing the rounds on the Mersey
waterfront since the Christmas holidays that problems were being
experienced with the new Cruise Terminal landing stage extension.
"Scuttle butt" at the time suggested that water had entered Canada
Dry Dock during the holiday period putting the project behind
schedule. The project should have been completed in time for
the first scheduled "walk ashore" call to be made by the MAASDAM on
July 29.
It became apparent during June that the stage was due to be installed on the river in
sections from June 23 onwards. However, that date came and went. It
was later announced that the stage would be taken on to the river
towards the end of July when the tides were suitable. At this point
it was admitted in the press that it wouldn't be ready for the MAASDAM.
However, by mid July
www.irishseashipping.com had received several reports from
correspondents that pieces of concrete had started to fall off the
structure - possibly due to the concrete not setting properly as a
result of water ingress into Canada Dry Dock over the Christmas
Holiday period? Apparently putting the structure back in
Canada Dock was not an option as it was believed that some damage
was caused to the gate opening mechanism when it was extracted,
furthermore, Canada Dock is reported to be the location of the
recycling of HMS INTREPID by
Leavesley International commencing in the near future.
On Saturday August 04, two sections stage were towed across the river from Canada
Dock to Cammell Laird #5 dry dock by Smit tugs. The first being
moved in the early hours under the cover of darkness, the second
during the afternoon.
To date there has been no public comment by the
contractors nor Liverpool City Council - however - the Saturday
afternoon towing operation would not have gone unnoticed. One
imagines that an official announcement concerning problems and
delays won't be long coming.
The big question is - will the cruise terminal
be ready for the arrival of the PRINSENDAM on September 02 or even
the official
opening when QUEEN ELIZABETH 2 calls on September 21 - let
along the other calls scheduled for SEVEN SEAS VOYAGER, OCEAN
MAJESTY or DEUTSCHLAND all due in September?
Any admission of problems will come as a
serious embarrassment for Liverpool City Council who are responsible
for the terminal following the sudden announcement that the popular
Mathew Street Music Festival due later this month has been
cancelled due to the unavailability of the waterfront due to
construction works causing health and safety concerns.
|
 |
How it should have looked by
now (left).
The other pictures show the
second section en route to, and after arrival at Cammell Laird to
join the first section on Saturday August 04, 2007. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
|
Prince's
Landing Stage Works - Building the new road access bridge
August 04, 2007
Photographs © John H. Luxton |
 |
 |
 |
 |
 |
|
Construction of the new vehicle access bridge
commenced during the last week in July. This picture shows
construction of the bridge underway on Saturday August 04, 2007. It
is being constructed over the vehicle marshalling area constructed
in the floating roadway cut. Presumably once complete it will be
drawn forward and dropped into place. Those who have long
memories and remember the old 1960's Pier Head bus station may
recall the small garden located near the floating roadway which had
a small pond. In the middle of which was a wrought iron structure
which your web master thinks bore a plaque inscribed "The Seven
Seas" - well it appears to have been "found" and looks as it was
sitting in the works compound on Saturday awaiting reinstallation. |
|
Prince's Stage Works Cruise Terminal
Extension
July 14, 2007
Photographs © John H. Luxton
|
 |
 |
 |
 |
 |
|
The almost completed vehicle marshalling area for
the Isle of Man Steam Packet Company in St. Nicholas' Place can be
seen on the left. The centre view shows the work underway to provide
the foundations on the existing stage for the new vehicle access
bridge, which in addition to providing access to the stage for Steam
Packet sailings will also provide access to the Cruise Terminal
extension for coaches. The top right photograph is of particular
interest as it shows the landward foundations, however, at low
water, as seen on Sunday July 15, a large section of concrete has
fallen away - compare with the photograph of the foundations taken
on April 21 (below). This may well be by design or it may not - if
anyone knows please email
irishseashipping@btinternet.com. On Wednesday July 18 the
anchoring point for the extension was being fixed to the north
end of the existing stage. |
|
The Stage
Extension is Floated Out
June 16, 2007
Photographs © John H. Luxton & George Jones
|
 |
 |
 |
 |
Floating out of the first of the new sections of
Prince's Landing Stage which will comprise the City of Liverpool
Cruise Terminal commenced at around 10:15 on June 16, 2007 with
tugs SMIT WATERLOO and SMIT LIVERPOOL in attendance. |
 |
 |
 |
 |
 |
 |
 |
 |
SMIT WATERLOO and SMIT LIVERPOOL
manoeuvre the second
section of the stage into Canada #1 Branch Dock on the afternoon of
June 16. Photographs © George Jones. |
|
Prince's Stage Works Cruise Terminal
Extension Floats - June 13, 2007
Photographs
©
Dan Cross
|
|
|
|
|
|
|
 |
 |
 |
 |
 |
 |
 |
On June 13, Canada Graving Dock
was flooded and the new Prince's Landing Stage extension, which will
comprise the City of Liverpool Cruise Terminal floated. These
photographs show the stage lifting off the bottom of the dock and
clearly show the means of anchorage to the the dolphins. - Photos:
Dan Cross. |
|
Prince's Stage Works In Progress - May 30, 2007 |
 |
 |
 |
 |
 |
|
On May 30, 2007 back hoe dredger MANU-PEKKA was busy
filling the hopper barge LONG SAND with at the northern end of the
site for the new landing stage extension. Meanwhile at the southern
end a Bay Towage survey boat was undertaking a survey of the river
bed moving backwards and forwards across the site of the new stage. |
|
Prince's Stage Works In Progress - May 12, 2007 |
 |
 |
 |
On May 12, 2007 work was underway cleaning the
pilings which will act as anchors for the Liverpool Cruise Terminal
extension to Prince's Landing Stage.
Some of the pilings have now gained finial
caps. |
 |
 |
 |
 |
The road system in St. Nicholas Place is rapidly
taking shape with the new road way now open to traffic and the
marshalling area and short stay car park facility being completed. |
|
Prince's Stage Works In Progress - April 21, 2007 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
|
The scene on Saturday April 21,
2007. The Isle of Man Steam Packet car marshalling area constructed
on the floating roadway site is now virtually complete. It is clear
where the bridge will be mounted leading down to the landing stage.
The construction of the pilings against which the new landing stage
extension will rise and fall is now well underway. The actual piling
appear to be created by inserting a cofferdam in the river bed and
pouring concrete into it. On the morning of Saturday April 21, the
cofferdam could be seen being lifted into position by crane mounted
on the barge SAMBA. By 20:00 the same evening the cofferdam was in
place and concrete was being poured from Commercial Marine & Piling
Ltd's jack up rig |
|
Prince's Stage Works In Progress - April 08, 2007 |
 |
By Saturday April 08, 2007 the
Steam Packet marshalling area had been given a block paved surface,
laid on top of the tar seen below. The traffic lanes being marked by
different coloured blocks. Meanwhile Commercial Marine & Piling's
spudjack barge SAMBA was working on installing anchoring columns for
the stage extension on Wednesday April 04 (right). |
 |
 |
|
Prince's Stage Works In Progress - February 24, 2007 |
 |
 |
 |
Surfacing of the IoMSPCo
marshalling area has been completed and the top of the
Pier Head Canal tunnel covered (left). The piling of the old
terminal buildings (see below) has been completely removed. The jack
up platform, now undertaking work in connection with the
installation of the landing stage extension. (right). |
 |
|
Prince's Stage Works In Progress - January 27, 2007 |
|
This page will record the development works
associated with the new Prince's Stage extension during the winter
of 2006 / 07. |
 |
 |
 |
 |
 |
 |
By Saturday January 27, 2007 filling
in of the floating roadway cut was complete. Traffic has now been
diverted through what is likely to become the Isle of Man Steam
Packet Company vehicle check in area. Construction of the northern
section of the canal link tunnel now appears to be underway.
Meanwhile Commercial Marine &
Piling Ltd's jack up rig has been working at removing the timber
supports for the former terminal buildings which served the old
timber Prince's Landing Stage. A close up photograph of where some
of the cross ties have been severed (top right) reveals that this
old timber appears to be in remarkably good condition. |
|
Prince's Stage Works
In Progress - December 23, 2006 |
|
|
|
|
|
|
 |
 |
 |
 |
 |
|
By late December the floating roadway cut between
the canal tunnel and St.Nicholas Place has been filled in. Surfacing
is underway in the vehicle marshalling area. |
|
Prince's Stage Works
In Progress - December 09, 2006 |
 |
 |
 |
 |
 |
|
New Portacabins have appeared, whilst the last remains
of the old Steam Packet Terminal buildings mainly removed in the
summer have now disappeared. |
Is the Steam Packet trying to tell Mersey Ferries
something about the use of Prince's Stage? |
Mersey Ferries Passengers waiting to board ROYAL
DAFFODIL on December 09, 2006. |
Commercial Marine Piling's Jack Up Platform working
on the Prince's Stage Extension site |
Workboat JESSICA S alongside Prince's Jetty. Not many
vessels have berthed here in recent years! |
|
Floating Roadway Cut & Prince's Stage Works
In Progress - November 25, 2006 |
|
 |
 |
 |
The former floating roadway cut
photographed on November 25, 2006 showing the almost complete
"tunnel" for the proposed Princess Dock - Canning Dock Canal.
The space riverward from the
"tunnel" has been back filled to the dam which was installed in
September with what looks to be material from the mountain of spoil
which has built up on the site of Trafalgar Dock. |
|
Work in progress on Prince's
Landing Stage. The concrete dam can be seen in the first photo
right. The second photo shows the remains of the former IoMSPCo
ticket office which was mainly demolished during the summer. Finally
contractors can be seen (far right) completing work to facilitate
the use of Prince's Stage by Mersey Ferries once again. |
 |
 |
 |
 |
 |
On Friday November 24, MERSEY
MAMMOTH removed the "bailey bridge" which provided the link to the
Ravestein SKYLINE BARGE 15. It is expected that the temporary stage
will be removed week beginning November 27. The plan to relocate the
barge south of the Prince's Stage has been postponed due to
difficulties experienced in recovering the floating structure. |
|
Work In
Progress on the Floating Roadway Cut - October 21, 2006 |
 |
 |
 |
 |
Work in progress in the
Floating Roadway cut at Liverpool on October 21, 2006 in connection
with the Prince's Landing Stage improvements. The excavations
each side of the cut appear to be on the line of the proposed
Princes Dock - Albert Dock Canal Link. |
 |